When a contractor hands over your fit-out, factory or building works, your company usually still holds a retention sum and has a defects liability period (DLP) in which the contractor must put defects right. Your rights come mainly from the contract. If defects appear, give written notice within the DLP, let the contractor try to rectify, keep evidence, and think carefully before withholding or set-off. Release the retention when the contract says so, and not before you have checked for unresolved defects.

What are a defects liability period and a retention sum?
A defects liability period is a contractual window after completion (often called substantial completion or handover) during which the contractor must return and repair defects at its own cost. The length, the notice method and what counts as a defect are all set by your contract, so read the clause rather than assume a standard period.
A retention sum is money the company holds back from the contractor’s payments as security. Contracts typically release part of it at completion and the balance after the DLP ends, but the split and the triggers differ from contract to contract. In one decided Singapore case, the retention was a percentage of the contract sum and half was due for release in the penultimate payment claim, with the rest tied to later events under the contract (CHL Construction Pte Ltd v Yangguang Group Pte Ltd [2019] SGHC 62).
The two work together. The DLP gives the contractor a chance to fix problems. The retention gives the company leverage if it does not.
What should the company do when a defect appears?
- Check the dates. Confirm the completion date and the last day of the DLP from the certificate or handover record.
- Record the defect. Take dated photographs and videos, note the location and write a short description. Keep any engineer, architect or consultant report.
- Give written notice. Follow the notice clause exactly: who receives it, by what method and with what details. Send it inside the DLP, and keep proof of delivery.
- Allow access to rectify. Many contracts require the company to give the contractor a reasonable opportunity to fix the defect before the company hires someone else.
- Chase and document. Follow up in writing. If the contractor does not respond, give a final notice stating what you will do next, such as engaging another contractor and recovering the cost.
- Get quotations. If the contract allows the company to rectify at the contractor’s cost, obtain at least one written quotation and keep invoices.
Can the company withhold the retention or set off defect costs?
Only if the contract or the law allows it. Many construction contracts give the company a right to deduct the cost of rectification from sums due. Whether you can use that right, and when, turns on the exact wording, on whether the defects were notified in time and on whether the contractor was given the chance the contract requires.
Withholding money without a contractual basis can expose the company to a claim for the unpaid sum. A company that deducts a vague or inflated figure may find the contractor suing for the balance and arguing breach. Set-off in a court claim also has its own rules, which we explain in our guide to counterclaim and set-off when your company is sued.
If you hold back money, state in writing which defects it covers, how you calculated the figure and which contract clause you rely on.
How does the Security of Payment Act affect retention and defects?
If your contract is a construction contract covered by the Building and Construction Industry Security of Payment Act 2004 (the SOP Act), the contractor may serve a payment claim, and the company then has a short statutory window to serve a payment response. Reasons for withholding that are not stated in the payment response may be barred from adjudication (the case law refers to s 15(3)). Our guide on responding to a payment claim from a fit-out contractor covers the deadlines.
Two points matter here. First, the court in Rong Shun Engineering & Construction Pte Ltd v C.P. Ong Construction Pte Ltd [2017] SGHC 34 set aside the part of an adjudicator’s award that dealt with a retention sum which the claimant had deducted from its own payment claim. In practice, a retention sum is only adjudicable if it forms part of the payment claim. Second, a contractor who claims released retention through the SOP Act will expect the company to say, within the payment response, if defects justify withholding.
Because statutory timelines are strict, treat any document labelled as a payment claim as urgent. The contractor’s route is explained in our contractor’s guide to adjudication, and our article on setting aside an adjudication determination explains the limited challenges available afterwards.
What are the common positions, and what do they mean?
| Situation | Usual position under the contract | What the company should do |
|---|---|---|
| Defect found inside the DLP | Contractor must rectify after notice | Serve written notice, give access, record everything |
| Contractor ignores the notice | Contract may let the company rectify and recover the cost | Give a final notice, obtain quotations, then proceed as the clause permits |
| Defect found after the DLP ends | The contractual repair duty may have lapsed, but a claim for damages may still exist | Get expert advice on cause and timing, and review the limitation position |
| DLP ended with no defects notified | Retention is normally due for release | Inspect before the final date and release as the contract provides |
| Contractor claims retention under the SOP Act | Strict statutory timelines apply | Serve a complete payment response on time |
Can the company claim for defects after the DLP has ended?
Possibly. The DLP defines the contractor’s contractual duty to return and repair. It does not necessarily remove the company’s right to sue for breach of contract or in negligence for defective work. Latent defects, which could not reasonably have been seen at handover, are the usual difficulty.
Time limits then matter. The Limitation Act 1959 generally allows six years for a contract claim from when it arose (s 6). For negligence claims involving latent damage, ss 24A and 24B contain separate rules, including a long-stop period, but the exact periods depend on when the damage appeared and when the claimant had the required knowledge. We have not set out those periods here because the application is fact-specific, and a lawyer should check the current statutory text for your dates. For a general view of time limits on business claims, see our guide to the limitation period for unpaid business debts.
If the claim is really about an adviser or consultant who supervised the works, our article on professional negligence claims may be relevant.
Which documents should the company keep?
- The signed contract and all variations, including the DLP and retention clauses.
- The completion or handover certificate and any punch list.
- Payment certificates, invoices and proof of retention deducted.
- Defect notices, replies, emails and WhatsApp messages with delivery proof.
- Dated photographs, videos and inspection or engineer reports.
- Quotations and invoices for any rectification you carry out.
- Board minutes or director approvals for withholding money.
Example: a retail unit fit-out
Example: A company has a shop fit-out completed on 1 March. The contract has a 12-month DLP and half the retention released at completion. In July, the flooring lifts. The company photographs the damage, sends written notice to the contractor’s named address and email, and asks for rectification within 14 days. The contractor does not attend. After a final notice, the company obtains a quotation and has the floor repaired, as the contract allows. When the contractor later claims the balance of the retention, the company deducts the documented repair cost, attaches the invoice and cites the clause. The company pays the rest. It has kept every notice, so a dispute over the amount would be decided on evidence rather than on competing accounts.
Frequently asked questions
Does the DLP end my right to complain about defects?
Not necessarily. It usually ends the contractor’s duty to return and repair under the contract, but a damages claim may still exist, subject to limitation periods. Defects reported inside the DLP are much easier to prove.
Can we release retention early?
Yes, if the contract or a signed variation allows it. Release only after checking for unresolved defects, because paying early can weaken your leverage.
What if the contract has no DLP clause?
Your rights then rest on the general law of contract and negligence, and on any warranty terms. Keep the same evidence and get advice on timing.
Can a contractor sue for retention while defects are outstanding?
It can try. Whether it succeeds depends on the release clause, whether defects were notified and whether you are entitled to set off the rectification cost. A clear written record helps.
Does the SOP Act apply to every renovation?
No. Whether it applies depends on the type of contract and works, so check this before deciding how to respond to a payment claim.
Need help with a contractor defects or retention dispute?
If your company, or you as a director or shareholder, is dealing with a contractor defects or retention dispute, contact the Raffles Corporate Services team at [email protected] or on WhatsApp at +65 8501 7133 or +65 9018 0072. We will help you understand the documents and deadlines. Where your matter needs a lawyer, we will refer you to a firm on our panel of Singapore law firms that regularly handles construction and commercial disputes. Raffles Corporate Services is a corporate services provider, not a law firm, and this article is general information, not legal advice.
The Raffles Corporate Services Editorial Team, Raffles Corporate Services